26-0517: A resolution approving a proposed Contract between the City and County of Denver and DURAN EXCAVATING, INC. for the Tennessee & Oneida Storm System Phase 3 that will relieve flooding, relocate sanitary mains, include asphalt paving, and miscellaneous concrete flatwork restoration, in Council Districts 5 & 6 . Approves a contract with DURAN EXCAVATING, INC. for $5,928,075.00 with a term of NTP + 270 Days for the Tennessee & Oneida Storm System Phase 3 that will relieve flooding, relocate sanitary mains, include asphalt paving, and miscellaneous concrete flatwork restoration, in Council Districts 5 & 6 (DOTI-202582578). The last regularly scheduled Council meeting within the 30-day review period is on 5-18-2026. The Committee approved filing this item at its meeting on 4-22-2026.