Colfax Street Sewer Extension
OtherAI Summary
The City of Evanston will install a storm sewer extension on Colfax Street between Hartrey Avenue and Brown Avenue as part of the 2025 Alley and Sidewalk Improvements Project, with work beginning within two weeks of July 22, 2025. Construction will include pavement saw cutting, trench excavation, storm sewer installation, street patching, and parkway restoration, with daytime work hours from 7:00 AM to 5:00 PM requiring parking prohibitions. Temporary "No Parking" signs will be posted at least 48 hours before work begins, and street sweeping parking restrictions will be waived for one block radius around the construction zone. Alliance Contractors, Inc. is the project contractor, and the City's Capital Planning & Engineering Bureau will monitor the project under Resident Engineer Brooke Tucker's supervision.