Lee Street from Dodge Avenue to Florence Avenue
OtherAI Summary
The City of Evanston's 2025 Alley and Sidewalk Improvements Project will improve pedestrian infrastructure on Lee Street from Dodge Avenue to Florence Avenue over four to six weeks beginning within two weeks of July 7, 2025. Work includes pedestrian crossing improvements at Dodge Avenue, new sidewalk installation on the south side of Lee Street east of Dodge Avenue, sidewalk improvements throughout the project limits, and parkway restoration as needed. Daytime parking will be prohibited from 7:00 AM to 5:00 PM during construction, with street sweeping restrictions waived for one block around the construction zone. Alliance Contractors, Inc. is the project contractor, and construction notice signs will be posted at least 48 hours in advance of work start.